Posted on August 22, 2016 at 9:56 AM by Chelsey Gordon
Street Lights: Final connections are being made to the street light system.
Roadway: The top lift of asphalt has been installed. Irrigation repairs are still being made as needed with notice from residents.
Final project clean up and and outstanding repairs will begin this week.
Posted on July 18, 2016 at 3:36 PM by Chelsey Gordon
Streetlights: Installation of streetlights is near completion for the project.
Roadway: The contractor is currently repairing damaged curb sections before the final lift of asphalt is installed. Irrigation and sod restoration is also underway.
Final project completion is anticipated soon.
Posted on June 14, 2016 at 9:12 AM by Chelsey Gordon
Storm Pipe: Installation of the Storm system is now complete.
Potable Water Main: All new potable water mains and service lines are complete and in service.
Roadway: All of the roadbase and curb installation has been completed within the project limits. The first lift of asphalt still needs to be installed at the intersections of Ocala and Palmetto as well as Sarasota and Palmetto. The last remaining sidewalk ramps are in the process of being formed up and poured, before the final lift of asphalt is installed. Restoration of irrigation systems and final grading for sod are currently underway.
Street lights: Installation of the new street lighting system is on going at this time.