Bayview Progress Update

Posted on February 1, 2016 at 3:24 PM by Christine Nicole

Storm Pipe:

All of the storm pipe has been installed on Bayview Dr. to north of Ocala Rd.  Storm pipe installation continues on Orlando Rd.  Storm structures and pipe are currently being installed at the intersection of Orlando Rd. and Palmetto Rd.

Potable Water Main:

New potable water main and service lines are continuing to be installed along Bayview Dr.  The segment from Sarasota Rd. to Ocala Rd. has been installed, tested, and put into service.  The next segment north of Ocala Rd. (north to the bridge) is still being installed and tested.


Roadway:

Road base and curb construction continues on Bayview Dr.  The segment of road between Orlando Rd. and Sarasota Rd. has been done and the first lift of asphalt has been laid.  The contractor is currently grading and preparing the area between Sarasota Rd. and Ocala Rd. for road base and curb.  Restoration of irrigation and sod is being completed as soon as each segment of roadway is paved.


Street Lights:

The street lights and poles are being reinstalled as segments of roadway are paved