Project Overview
To increase pedestrian safety throughout Belleair, new crosswalks were added along Indian Rocks Road in 2020. The construction of these crosswalks was a three-step process:
- Damaged sidewalks and curbs along Indian Rocks Road were replaced and upgraded in the summer of 2020
- In September, crossing locations were milled and resurfaced. This means the top layer of asphalt was removed and resurfaced with a new layer of asphalt - this was done since the new striping must be applied to a fresh, smooth surface. The asphalt then had to set for several weeks before the next step
- Patterned surfaces and reflective striping was added to several crossings in November and December of 2020
Questions?
While this work was completed by a contractor, questions may be directed to Belleair's Construction Project Supervisor, Keith Bodeker: (727) 408-4860. Residents may also email Mr. Bodeker with questions or concerns.